What is an inline inspection report, and how is it different from a final inspection report?
An inline inspection report records a quality check made while the order is still being sewn; a final inspection report records the check of the finished, packed lot before it ships. The difference is what each one decides. A final random inspection draws its sample from the whole order, usually once at least 80% of it is packed, and decides whether the lot is accepted for shipment against AQL limits. An inline or during-production check draws its sample from the pieces that exist on the day, and decides what has to be corrected before the rest is sewn. That is why this template has no pass or fail line: each finding gets an action, an owner and a re-check date, and the report ends with a status, which is carry on, carry on with actions, or stop and correct. The final inspection still follows, and its inspector should read the inline report first.
When should a during-production inspection be done?
Early enough that a fault can still be fixed on most of the order, and late enough that the line is running at normal speed. Inspection companies set a threshold: QIMA makes a during-production inspection when at least 20% of the order is complete, and HQTS describes around 20%. On a clothing order the first bundles off the line are the cheapest moment to find a construction or measurement fault, because only a few hundred pieces carry it. Inside the factory, roving quality checkers check each operator throughout sewing, and their sheets are worth asking to see. Write the visits you want into the order confirmation, with their timing: an inline or initial production check on the first bundles, a during-production inspection at about a fifth of the order, and the final inspection when the order is finished and mostly packed. In the template’s example the visit comes at 40% sewn, with the whole order already cut.
How many pieces should an inline inspection check?
For a buyer’s or a buying house’s inspector, take the sample from the same AQL table as the final inspection, applied to the quantity made so far rather than the order quantity; QIMA, for example, draws its during-production sample following ANSI/ASQ Z1.4, the American counterpart of ISO 2859-1. In the template’s example, 1,152 pieces are sewn on the day, and general inspection level II gives a sample of 80 pieces, which the AQL calculator works out for any quantity. Pick them across lines, sizes and colours, from finished bundles and from pieces still at the machines. A roving checker inside the factory works differently and checks a few pieces of each operator’s work; in the common “7.0 system” the checker takes seven garments and marks the operator red if even one is faulty. For each finding, the template records how many pieces were checked for that point and how many were faulty.
What should happen after an inline inspection finds a problem?
Fix the cause, not only the pieces, and prove the fix with a re-check. A wavy neck usually comes from machine tension, feed or the operator’s handling; a measurement drift usually starts before the line, in the pattern, the marker or the cutting, so the action belongs where the cause is. Then go back to the last good check: every bundle sewn since then may carry the same fault, and those pieces should be checked and repaired or rejected. Give every finding an owner and a re-check date, because a finding without a date tends to stay open. Tell the buyer the same day when the specification is affected, such as colour, measurements, artwork or labels, and stop the line when a fault affects every piece being made. Finally, carry the findings to the final inspection, so its inspector checks that they were fixed across the whole lot.
Is there an inline inspection report format in Excel for garments?
Yes: this garment inline inspection report downloads as a free Excel file, with no sign-up, and it also opens in Google Sheets. It has two sheets, the blank template and an example filled in for a fictional order of 2,880 t-shirts, and its grey cells work out the share of the order sewn and count the measurements outside tolerance. The layout follows the inspector on the line: order and progress, the sample, checks against the approved sample, findings with their actions, measurements, packing if it has started, and status and sign-off. A printable version is on the same page. Once the order is finished and packed, the final inspection report template takes over, with the AQL accept and reject numbers.
What production progress should an inline inspection report record?
An inline inspection report should record four counts: pieces cut, pieces sewn, pieces finished and pieces packed, counted by the inspector rather than copied from the factory’s board. Those four numbers show whether the delivery date still holds, and they let the next report show whether the line caught up or fell further behind. In the template’s example, all 2,880 pieces are cut, 1,152 are sewn (40% of the order, which the Excel file works out), 576 are finished and none are packed. The report also names the factory, unit and sewing lines, the sealed sample and tech pack revision used as the reference, and whether the planned completion date is still on schedule.
When should an inline inspection stop the sewing line?
Stop the line when a fault affects every piece being made, such as a print in the wrong place or a measurement out on every piece; carry on with actions when the fault is limited and the fix is in place. Those are the three statuses the template ends with: carry on, carry on with the actions above, or stop and correct. In the example, the chest print was 1.5 cm low on all 20 pieces checked, so printing was held until the screen was re-registered, while the rest of the line carried on with the agreed actions. Tell the buyer the same day when the specification is affected, and whatever the status, write the date of the next check: the re-check is what shows the fix worked.
Should an inline inspection check packing and carton marks?
Yes, if packing has started: check the first cartons during the inline inspection, because a wrong carton size, carton mark or barcode found then costs a morning, while found at the final inspection it means repacking the whole lot. Check the carton size, marks and assortment against the packing instructions, the polybags for size, thickness, closure and printed warning, the barcodes and stickers, and the folding. When nothing is packed yet, write N/A and check the packing materials waiting to be used instead; in the template’s example, the polybags were checked on the stock waiting for packing and the sticker proofs against the purchase order. Carton marks and barcodes are the most common reason a lot that passed on quality still cannot ship.
Which checks against the sealed sample matter most at an inline inspection?
The checks that matter most are those that are cheap to fix on the line and expensive at the final inspection: shade between bundles and between the panels of one garment, the position and colour of prints, every label, and the trims. Judge shade under the light source agreed in the order. Keep reading labels after the first pieces, because care and fibre labels are sewn in from rolls and a new roll can be the wrong one. The template also checks style and construction, fabric weight, and stitch density, seam allowance and thread tension; in the example the side seam had 12 stitches per 3 cm, as specified. Mark a check Fail even when the fault is being corrected, so the report shows what was found on the day.
Should inline inspection measurements be taken on pressed or unpressed garments?
Measure finished or pressed pieces, or note on the report that they were not, because pressing changes some measurements and a piece straight off the machine will not compare fairly with a finished-garment size chart. Measure the sizes being sewn on the day, up to five pieces each, on the points of measure that decide fit, and copy the specification and tolerance from the tech pack revision named on the report. The Excel file counts the readings outside tolerance. In the template’s example, 3 of 5 size M pieces were over the 1.0 cm tolerance on body length, and the action was to check the pattern and marker against the approved size set, since a drift found inline usually starts before the sewing line.